Northhampton, NC interconnection queue
5 active projects totalling 313.4 MW in the PJM queue, plus 13 with terminal status (shown greyed).
5active projects
313.4active MW
18total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| AC2-093 | Brunswick-Wake 500 kV | 500 | 429.4 | Solar | Withdrawn |
| AC1-086 | Cherry Solar | 230 | 123.7 | Solar | Partially in Service - Under Construction |
| AB1-132 | Oak Solar | 230 | 84 | Solar | In Service |
| AB2-128 | Clubhouse-Lakeview 230kV | 230 | 57.4 | Solar | Withdrawn |
| AA1-064 | Carson-Wake 500kV | 500 | 56 | Solar | Withdrawn |
| AA1-137 | Earleys-Northampton 230kV | 230 | 56 | Solar | Withdrawn |
| AA2-181 | Earleys-Northampton 230kV | 230 | 56 | Solar | Withdrawn |
| AA2-053 | Gutenberg Solar | 115 | 52.4 | Solar | In Service |
| AA1-063A | Spuds Lane Solar Park | 115 | 50.9 | Solar | In Service |
| AH1-434 | ACE Development Company, LLC | 115 | 45 | Solar | Withdrawn |
| AC2-159 | Jackson-Woodland 115kV | 115 | 40 | Solar | Withdrawn |
| AH1-435 | Carolina- Earleys 115kV | 115 | 30 | Battery | Withdrawn |
| AG1-313 | Jackson DP-Occoneechee 115 kV | 115 | 27.6 | Solar | Withdrawn |
| AG1-106 | Oak Solar | 230 | 16 | Solar | Withdrawn |
| AG1-552 | Ray Solar | 34.5 | 12.2 | Solar | Withdrawn |
| AA2-149 | Carolina-Seaboard 115kV | 115 | 7.6 | Solar | Withdrawn |
| AA2-174 | Gutenberg Solar | 115 | 2.4 | Solar | In Service |
| AG2-237 | Thelma 230kV | 230 | 0 | Battery | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.