Midland Wind Farm
PJM queue ID AC1-033
Midland Wind Farm (AC1-033) is listed in the PJM interconnection queue as a 13.1 MW wind project in Henry County, IL. The filing names Kewanee as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of April 15, 2024.
| Queue ID | AC1-033 |
|---|---|
| Project name | Midland Wind Farm |
| Status (as published) | In Service |
| Substation | Kewanee |
| Point of interconnection | Kewanee 138 kV |
| County | Henry |
| State | IL |
| Voltage | 138 kV |
| Capacity | 13.1 MW |
| Resource (as published) | Wind |
| Resource category | Wind (normalized for filtering) |
| Target commercial operation | 2024-04-15 |
| Source dataset | serial |
Same substation and county
Kewanee substation: 6 requests in the PJM queue, 2 active totaling 53.1 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| P11 | Bishop Hill WF | 40 | Wind | In Service |
| Q60 | Kewanee 138kV | 40.2 | Wind | Withdrawn |
| Q39 | Kewanee 138kV | 21 | Wind | Withdrawn |
| AA2-039 | Kewanee 138 kV | 19.5 | Wind | Withdrawn |
| W3-133 | Kewanee | 2.5 | Wind | Withdrawn |
Henry, IL: 9 requests in the PJM queue, 2 active totaling 79.3 MW.
A substation with the same name is named in PJM transmission planning materials: Kewanee (COMED, 4 mentions).
Same name and state (weaker). Matched on name and state: the utility that presented this substation operates in one state, and every queue filing at a substation of the same name is in that state. No transmission owner is recorded on those filings, so this is a weaker match than one on owner. Not verified as the same facility.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 100.8 |
| MW capacity | 13.1 |
| MFO | 100.8 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.