Substation Scout

Peach Bottom Units #2 & #3

PJM queue ID AB2-175

Queue IDAB2-175
Project namePeach Bottom Units #2 & #3
Status (as published)Partially in Service - Under Construction
SubstationPeach Bottom
Point of interconnectionPeach Bottom 500kV
CountyYork
StatePA
Voltage500 kV
Capacity44 MW
Resource (as published)Nuclear
Resource categoryNuclear (normalised for filtering)
Target commercial operation2018-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy44
Mw Capacity44
Mfo2709.8

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.