5 active projects totalling 79.1 MW in the PJM queue, plus 10 with terminal status (shown greyed).

5active projects
79.1active MW
15total filed
Queue IDProjectkVMWResourceStatus
AF2-066 West Manchester-Crown 69kV 69 48 Solar Withdrawn
AI2-238 College Corner 138 kV 138 39.4 Solar Withdrawn
AC2-111 Angelina Solar I 138 30.4 Solar Engineering and Procurement
AI2-240 Camden - Crystal 69 kV 69 25.3 Solar Withdrawn
AF2-067 West Manchester 69 kV 69 24 Solar Withdrawn
AI2-397 West Manchester-Crown 69kV 69 19.2 Solar Withdrawn
AC2-067 Eaton OH Solar 69 18.9 Solar Under Construction
AG1-049 College Corner 138 kV 138 17.6 Solar Withdrawn
AG2-125 Camden-Crystal 69 kV 69 15.4 Solar Active
AI2-398 West Manchester 69 kV 69 9.6 Solar Withdrawn
AC2-068 Eaton OH Solar 69 7.6 Solar Under Construction
AE1-007 Camden-Crystal III 69 kV 69 7.6 Solar Withdrawn
AE1-008 College Corner 138 kV 138 7.6 Solar Withdrawn
W2-040 Preble Solar Energy 69 7.6 Solar Withdrawn
AF1-071 Angelina Solar I 138 6.8 Solar Under Construction