Camden-Crystal 69 kV
PJM queue ID AG2-125
Camden-Crystal 69 kV (AG2-125) is listed in the PJM interconnection queue as a 15.4 MW solar project in Preble County, OH. The filing names Camden-Crystal as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of June 1, 2027.
| Queue ID | AG2-125 |
|---|---|
| Project name | Camden-Crystal 69 kV |
| Status (as published) | Active |
| Substation | Camden-Crystal |
| Point of interconnection | Camden-Crystal 69 kV |
| County | Preble |
| State | OH |
| Voltage | 69 kV |
| Capacity | 15.4 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2027-06-01 |
| Source dataset | cycle |
Same substation and county
Preble, OH: 15 requests in the PJM queue, 5 active totaling 79.1 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | Alamo Solar I, LLC |
|---|---|
| Transmission owner | DAYTON |
| Project type | Generation Interconnection |
| Cycle | TC2 |
| Stage | Phase 3 |
| MW energy | 0.0 |
| MW capacity | 15.44 |
| MFO | 69.9 |
| Submitted date | 1/29/2021 |
| Last updated | 9/2/2026 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.