South Justice - Dawsons Crossroads DP 115 kV
PJM queue ID C01-2145
South Justice - Dawsons Crossroads DP 115 kV (C01-2145) is listed in the PJM interconnection queue as a 100 MW hybrid project in Halifax County, NC. The filing names South Justice - Dawsons Crossroads DP as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of February 7, 2031.
| Queue ID | C01-2145 |
|---|---|
| Project name | South Justice - Dawsons Crossroads DP 115 kV |
| Status (as published) | Active |
| Substation | South Justice - Dawsons Crossroads DP |
| Point of interconnection | South Justice - Dawsons Crossroads DP 115 kV |
| County | Halifax |
| State | NC |
| Voltage | 115 kV |
| Capacity | 100 MW |
| Resource (as published) | Solar,Storage,Hybrid |
| Resource category | Hybrid (normalized for filtering) |
| Target commercial operation | 2031-02-07 |
| Source dataset | cycle |
Same substation and county
Halifax, NC: 22 requests in the PJM queue, 8 active totaling 355.8 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | Beech Sapling Solar LLC |
|---|---|
| Transmission owner | Dominion |
| Project type | Generation Interconnection |
| Cycle | C01 |
| Stage | Phase 1 |
| MW energy | 100.0 |
| MW capacity | 100.0 |
| MFO | 100.0 |
| Submitted date | 4/27/2026 |
| Last updated | 6/12/2026 |