Ridgeley - Frostburg 138 kV (C01-1874) is listed in the PJM interconnection queue as a 150 MW battery project in Allegany County, MD. The filing names Ridgeley - Frostburg as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of December 31, 2030.
| Queue ID | C01-1874 |
|---|---|
| Project name | Ridgeley - Frostburg 138 kV |
| Status (as published) | Active |
| Substation | Ridgeley - Frostburg |
| Point of interconnection | Ridgeley - Frostburg 138 kV |
| County | Allegany |
| State | MD |
| Voltage | 138 kV |
| Capacity | 150 MW |
| Resource (as published) | Storage |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2030-12-31 |
| Source dataset | cycle |
Same substation and county
Allegany, MD: 23 requests in the PJM queue, 6 active totaling 190.6 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | Frostburg Storage, LLC |
|---|---|
| Transmission owner | APS |
| Project type | Generation Interconnection |
| Cycle | C01 |
| Stage | Phase 1 |
| MW energy | 150.0 |
| MW capacity | 150.0 |
| MFO | 150.0 |
| Submitted date | 4/27/2026 |
| Last updated | 6/9/2026 |