TNCOYOTSPG1 substation interconnection queue
2 active projects totaling 313.5 MW in the ERCOT queue.
2 ERCOT queue filings name TNCOYOTSPG1 as the point of interconnection, all in Reeves County, TX.
Target commercial operation dates as filed run from Jun 2027 to Jun 2029 (2 filings). 2 active filings target a date after November 27, 2026.
Interconnecting entity as filed: Nanulak BESS, L.L.C. (1 filing), Hunt Energy Network, LLC (1 filing).
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| 26INR0385 | Nanulak BESS | 138 | 181.5 | Battery | SS Completed, FIS Completed, IA | Jun 2027 |
| 26INR0396 | Kodiak AGR1 | n/r | 132 | Other | SS Completed, FIS Started, No IA | Jun 2029 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.
Tracked changes at this substation
1 change to filings at this point of interconnection, observed between weekly snapshots of the ERCOT queue. For a capacity revision MW is the change, not the new total.
| Detected | Queue ID | Change | MW | Status was → now |
|---|---|---|---|---|
| 2026-09-07 | 26INR0385 | Status change | n/a | SS Completed, FIS Started, IA → SS Completed, FIS Completed, IA |
Other ERCOT queue substations in Reeves County, TX
- # Solstice Substation: 4 active, 2,707 MW of 4 filed
- Tap SOLSTICE - SANDLAKE_5: 4 active, 1,633.7 MW of 4 filed