TNCOYOTSPG1 substation interconnection queue

2 active projects totalling 313.5 MW in the ERCOT queue.

2active projects
313.5active MW
2total filed
Queue IDProjectkVMWResourceStatus
26INR0385 Nanulak BESS 138 181.5 Battery SS Completed, FIS Started, IA
26INR0396 Kodiak AGR1 n/r 132 Other SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.