Temple Pecan Creek substation interconnection queue
2 active projects totalling 254.6 MW in the ERCOT queue.
2active projects
254.6active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 23INR0249 | Limewood Solar | 138 | 204.6 | Solar | SS Completed, FIS Completed, IA |
| 23INR0248 | Limewood Storage | 138 | 50 | Battery | SS Completed, FIS Started, IA |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.