Tap Vosslake - Buckholts substation interconnection queue
2 active projects totaling 382.5 MW in the ERCOT queue.
2 ERCOT queue filings name Tap Vosslake - Buckholts as the point of interconnection, all in Milam County, TX.
Target commercial operation date as filed: Jul 2028 (2 filings). 2 active filings target a date after November 27, 2026.
Interconnecting entity as filed: San Gabriel Solar LLC (2 filings).
2active projects
382.5active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| 28INR0185 | San Gabriel Solar | 138 | 255 | Solar | SS Completed, FIS Completed, IA | Jul 2028 |
| 28INR0191 | San Gabriel Storage | 138 | 127.5 | Battery | SS Completed, FIS Completed, IA | Jul 2028 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.
Tracked changes at this substation
2 changes to filings at this point of interconnection, observed between weekly snapshots of the ERCOT queue. For a capacity revision MW is the change, not the new total.
| Detected | Queue ID | Change | MW | Status was → now |
|---|---|---|---|---|
| 2026-09-07 | 28INR0185 | Status change | n/a | SS Completed, FIS Completed, No IA → SS Completed, FIS Completed, IA |
| 2026-09-07 | 28INR0191 | Status change | n/a | SS Completed, FIS Completed, No IA → SS Completed, FIS Completed, IA |
Other ERCOT queue substations in Milam County, TX
- Bell County East Switch (bus# ) - TNP One (bus# ) circuit 2: 2 active, 395.5 MW of 2 filed
- Tap Voss Lake switch # – Badger Switch #: 2 active, 307.5 MW of 2 filed
- Tap Hog Creek Switch – Bell County East Switch: 2 active, 190 MW of 2 filed
- Line GRISTMILL_5 to TNTNP_ONE_3: none active of 2 filed