Line () GRISTMILL_5 to () TNTNP_ONE_3 substation interconnection queue
2 active projects totalling 486 MW in the ERCOT queue.
2active projects
486active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 29INR0163 | Brazos Bend Solar SLF | 345 | 243 | Solar | SS Completed, FIS Started, No IA |
| 29INR0164 | Brazos Bend Storage SLF | 345 | 243 | Battery | SS Completed, FIS Started, No IA |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.