Tap TONKAWAW_5 – SCURCNTYS_5 Circuit #2 substation interconnection queue
2 active projects totaling 568.2 MW in the ERCOT queue.
2 ERCOT queue filings name Tap TONKAWAW_5 – SCURCNTYS_5 Circuit #2 as the point of interconnection, all in Scurry County, TX.
Target commercial operation date as filed: Mar 2029 (2 filings). 2 active filings target a date after November 27, 2026.
Interconnecting entity as filed: Inadale BESS, LLC (1 filing), Inadale Solar, LLC (1 filing).
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| 25INR0197 | Inadale BESS | 345 | 287.2 | Battery | SS Completed, FIS Started, No IA | Mar 2029 |
| 25INR0196 | Inadale Solar | 345 | 281 | Solar | SS Completed, FIS Completed, No IA | Mar 2029 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.
Tracked changes at this substation
1 change to filings at this point of interconnection, observed between weekly snapshots of the ERCOT queue. For a capacity revision MW is the change, not the new total.
| Detected | Queue ID | Change | MW | Status was → now |
|---|---|---|---|---|
| 2026-09-07 | 25INR0196 | Status change | n/a | SS Completed, FIS Started, No IA → SS Completed, FIS Completed, No IA |
Other ERCOT queue substations in Scurry County, TX
- MHOS Substation (#): 2 active, 1,546.6 MW of 2 filed
- Nebula7A: 2 active, 677.1 MW of 2 filed
- DERMOTT: 2 active, 204.5 MW of 2 filed
- GALVANI 345: 2 active, 200 MW of 2 filed