Substation Scout

Tap TONKAWAW_5 – SCURCNTYS_5 Circuit #2 substation interconnection queue

2 active projects totaling 568.2 MW in the ERCOT queue.

2 ERCOT queue filings name Tap TONKAWAW_5 – SCURCNTYS_5 Circuit #2 as the point of interconnection, all in Scurry County, TX.

Target commercial operation date as filed: Mar 2029 (2 filings). 2 active filings target a date after November 27, 2026.

Interconnecting entity as filed: Inadale BESS, LLC (1 filing), Inadale Solar, LLC (1 filing).

2active projects
568.2active MW
2total filed
Queue IDProjectkVMWResourceStatusTarget COD
25INR0197 Inadale BESS 345 287.2 Battery SS Completed, FIS Started, No IA Mar 2029
25INR0196 Inadale Solar 345 281 Solar SS Completed, FIS Completed, No IA Mar 2029

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.

Tracked changes at this substation

1 change to filings at this point of interconnection, observed between weekly snapshots of the ERCOT queue. For a capacity revision MW is the change, not the new total.

DetectedQueue IDChangeMWStatus was → now
2026-09-0725INR0196Status changen/a SS Completed, FIS Started, No IA → SS Completed, FIS Completed, No IA

Other ERCOT queue substations in Scurry County, TX

All 23 ERCOT queue filings in Scurry County, TX.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first