Tap RICHLND2_5 - BIGBRNW_5 substation interconnection queue
2 active projects totaling 452.4 MW in the ERCOT queue.
2 ERCOT queue filings name Tap RICHLND2_5 - BIGBRNW_5 as the point of interconnection, all in Freestone County, TX.
Target commercial operation dates as filed run from Jul 2028 to Dec 2028 (2 filings). 2 active filings target a date after November 27, 2026.
Interconnecting entity as filed: Amerada Solar, LLC (2 filings).
2active projects
452.4active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| 26INR0082 | Amerada Solar | 345 | 301.6 | Solar | SS Completed, FIS Started, No IA | Dec 2028 |
| 26INR0084 | Amerada Storage | 345 | 150.8 | Battery | SS Completed, FIS Started, No IA | Jul 2028 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.
Other ERCOT queue substations in Freestone County, TX
- Tap Big Brown to Navarro ckt#2: 2 active, 455 MW of 2 filed
- Long Lake Sub (Bus ) – Long Lake Tap Switch (Bus ): 2 active, 200.3 MW of 2 filed
- Tap 212 Winkler - Pin Oak: 2 active, 100.5 MW of 2 filed