TAP LINE FROM TRADINGHOUSE (#) TO TEMPLE PECAN CREEK (#) SUBSTATIONS substation interconnection queue
2 active projects totalling 301.6 MW in the ERCOT queue.
2active projects
301.6active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 25INR0297 | RIVERBEND SOLAR SLF | 345 | 301.6 | Solar | SS Completed, FIS Started, No IA |
| 25INR0311 | RIVERBEND STORAGE SLF | 345 | 0 | Battery | SS Completed, FIS Completed, No IA |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.