Substation Scout

TAP LINE FROM TRADINGHOUSE (#) TO TEMPLE PECAN CREEK (#) SUBSTATIONS substation interconnection queue

2 active projects totalling 301.6 MW in the ERCOT queue.

2active projects
301.6active MW
2total filed
Queue IDProjectkVMWResourceStatus
25INR0297 RIVERBEND SOLAR SLF 345 301.6 Solar SS Completed, FIS Started, No IA
25INR0311 RIVERBEND STORAGE SLF 345 0 Battery SS Completed, FIS Completed, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.