Falls, TX interconnection queue

13 active projects totalling 1,509.2 MW in the ERCOT queue.

13active projects
1,509.2active MW
13total filed
Queue IDProjectkVMWResourceStatus
25INR0297 RIVERBEND SOLAR SLF 345 301.6 Solar SS Completed, FIS Started, No IA
20INR0205 Roseland Solar 345 254 Solar SS Completed, FIS Completed, IA
22INR0506 Roseland Solar II 345 254 Solar SS Completed, FIS Completed, IA
28INR0262 Pasture Rose Wind 345 198.7 Wind SS Completed, FIS Started, No IA
20INR0106 Wang Solar SLF 345 144.6 Solar SS Completed, FIS Started, No IA
24INR0040 Rosebud Solar SLF 69 130 Solar SS Completed, FIS Completed, No IA
25INR0440 Bronc Rodeo Solar Project 138 105.7 Solar SS Completed, FIS Completed, No IA
28INR0147 Fallstone Solar SLF 69 60.6 Solar SS Completed, FIS Started, No IA
29INR0105 Falls County Storage 345 60 Battery SS Completed, FIS Started, No IA
22INR0514 Wang Storage SLF 345 0 Battery SS Completed, FIS Started, No IA
25INR0311 RIVERBEND STORAGE SLF 345 0 Battery SS Completed, FIS Completed, No IA
25INR0341 Rosebud Storage SLF 69 0 Battery SS Completed, FIS Completed, No IA
28INR0149 Fallstone Storage SLF 69 0 Battery SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.