Substation Scout

RIVERBEND SOLAR SLF

ERCOT queue ID 25INR0297

Queue ID25INR0297
Project nameRIVERBEND SOLAR SLF
Status (as published)SS Completed, FIS Started, No IA
SubstationTAP LINE FROM TRADINGHOUSE (#) TO TEMPLE PECAN CREEK (#) SUBSTATIONS
Point of interconnectionTAP 345 KV LINE FROM TRADINGHOUSE (#3405) TO TEMPLE PECAN CREEK (#3412) SUBSTATIONS
CountyFalls
StateTX
Voltage345 kV
Capacity301.6 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2027-12-31
Source datasetlarge

Additional filed fields

Interconnecting EntityRiverbend Renewables, LLC
Cdr ZoneNORTH
Fuel CodeSOL
Technology CodePV
Screening Study Complete45082
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.