Tap Eagle Creek () to Floresville () substation interconnection queue
2 active projects totalling 375.8 MW in the ERCOT queue.
2active projects
375.8active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 28INR0299 | Moon Stone BESS | 138 | 200.8 | Battery | SS Completed, FIS Started, No IA |
| 24INR0156 | Moonstone Solar Project | 138 | 175 | Solar | SS Completed, FIS Completed, IA |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.