Substation Scout

Tap Eagle Creek () to Floresville () substation interconnection queue

2 active projects totalling 375.8 MW in the ERCOT queue.

2active projects
375.8active MW
2total filed
Queue IDProjectkVMWResourceStatus
28INR0299 Moon Stone BESS 138 200.8 Battery SS Completed, FIS Started, No IA
24INR0156 Moonstone Solar Project 138 175 Solar SS Completed, FIS Completed, IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.