Tap Eagle Creek to Floresville substation interconnection queue

2 active projects totaling 375.8 MW in the ERCOT queue.

2 ERCOT queue filings name Tap Eagle Creek to Floresville as the point of interconnection, all in Wilson County, TX.

Target commercial operation date as filed: Mar 2029 (2 filings). 2 active filings target a date after November 27, 2026.

Interconnecting entity as filed: Moon Stone Battery Facility LLC (1 filing), Moon Stone Solar Farm, LLC (1 filing).

2active projects
375.8active MW
2total filed
Queue IDProjectkVMWResourceStatusTarget COD
28INR0299 Moon Stone BESS 138 200.8 Battery SS Completed, FIS Started, No IA Mar 2029
24INR0156 Moonstone Solar Project 138 175 Solar SS Completed, FIS Completed, IA Mar 2029

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.

Other ERCOT queue substations in Wilson County, TX

All 18 ERCOT queue filings in Wilson County, TX.