Moonstone Solar Project
ERCOT queue ID 24INR0156
Moonstone Solar Project (24INR0156) is listed in the ERCOT interconnection queue as a 175 MW solar project in Wilson County, TX. The filing names Tap Eagle Creek to Floresville as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of March 31, 2029. It records the screening study as complete on January 24, 2022, the full interconnection study as approved on January 18, 2024 and the interconnection agreement as signed on February 17, 2025.
| Queue ID | 24INR0156 |
|---|---|
| Project name | Moonstone Solar Project |
| Status (as published) | SS Completed, FIS Completed, IA |
| Substation | Tap Eagle Creek to Floresville |
| Point of interconnection | Tap 138kV Eagle Creek (5132) to Floresville (5155) |
| County | Wilson |
| State | TX |
| Voltage | 138 kV |
| Capacity | 175 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2029-03-31 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Tap Eagle Creek to Floresville substation: 2 requests in the ERCOT queue, 2 active totaling 375.8 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| 28INR0299 | Moon Stone BESS | 200.8 | Battery | SS Completed, FIS Started, No IA |
Wilson, TX: 18 requests in the ERCOT queue, 15 active totaling 3,532.8 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | Moon Stone Solar Farm, LLC |
|---|---|
| CDR reporting zone | SOUTH |
| Fuel code | SOL |
| Technology code | PV |
| Interconnection agreement signed | 2025-02-17 |
| Screening study complete | 2022-01-24 |
| Full interconnection study approved | 2024-01-18 |
| Water availability | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.