Tap the Elm Creek (#) - Shaula (#) Line, CPS substation interconnection queue
3 active projects totalling 628.2 MW in the ERCOT queue.
3active projects
628.2active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 29INR0319 | Nockenut Springs Storage 2 | 345 | 209.4 | Battery | SS Completed, FIS Started, No IA |
| 29INR0320 | Nockenut Springs Storage 3 | 345 | 209.4 | Battery | SS Completed, FIS Started, No IA |
| 29INR0318 | Nockenut Springs Storage 1 | 345 | 209.4 | Battery | SS Completed, FIS Started, No IA |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.