Tap the Elm Creek (#) - Shaula (#) Line, CPS substation interconnection queue
3 active projects totaling 628.2 MW in the ERCOT queue.
3 ERCOT queue filings name Tap the Elm Creek (#) - Shaula (#) Line, CPS as the point of interconnection, all in Wilson County, TX.
Target commercial operation date as filed: Jun 2029 (3 filings). 3 active filings target a date after November 27, 2026.
Interconnecting entity as filed: Pecan Springs Energy, LLC (3 filings).
3active projects
628.2active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| 29INR0319 | Nockenut Springs Storage 2 | 345 | 209.4 | Battery | SS Completed, FIS Started, No IA | Jun 2029 |
| 29INR0320 | Nockenut Springs Storage 3 | 345 | 209.4 | Battery | SS Completed, FIS Started, No IA | Jun 2029 |
| 29INR0318 | Nockenut Springs Storage 1 | 345 | 209.4 | Battery | SS Completed, FIS Started, No IA | Jun 2029 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.
Other ERCOT queue substations in Wilson County, TX
- Tap Eagle Creek to Floresville: 2 active, 375.8 MW of 2 filed
- Tapping the Elm Creek to Shaula circuit 1: 2 active, 226.3 MW of 2 filed