Moon Stone BESS

ERCOT queue ID 28INR0299

Moon Stone BESS (28INR0299) is listed in the ERCOT interconnection queue as a 200.8 MW battery project in Wilson County, TX. The filing names Tap Eagle Creek to Floresville as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of March 31, 2029. It records the screening study as complete on May 14, 2025.

Queue ID28INR0299
Project nameMoon Stone BESS
Status (as published)SS Completed, FIS Started, No IA
SubstationTap Eagle Creek to Floresville
Point of interconnectionTap 138kV Eagle Creek (5132) to Floresville (5155)
CountyWilson
StateTX
Voltage138 kV
Capacity200.8 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalized for filtering)
Target commercial operation2029-03-31
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Tap Eagle Creek to Floresville substation: 2 requests in the ERCOT queue, 2 active totaling 375.8 MW.

Queue IDProjectMWResourceStatus
24INR0156Moonstone Solar Project175SolarSS Completed, FIS Completed, IA

Wilson, TX: 18 requests in the ERCOT queue, 15 active totaling 3,532.8 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityMoon Stone Battery Facility LLC
CDR reporting zoneSOUTH
Fuel codeOTH
Technology codeBA
Screening study complete2025-05-14

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first