Substation Scout

Tap DULCE7A - STATIC7A substation interconnection queue

3 active projects totalling 2,430 MW in the ERCOT queue.

3active projects
2,430active MW
3total filed
Queue IDProjectkVMWResourceStatus
33INR0007 Blue Energy Center - Phase 3 – Steam Stage 2 345 1,320 Nuclear SS Started, FIS Started, No IA
30INR0150 Blue Energy Center- Phase 1a - Gas 345 780 Gas SS Started, FIS Started, No IA
29INR0248 Blue Energy Center - Phase 1b – Steam 345 330 Gas SS Completed, FIS Started, No IA

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.