Tap DULCE7A - STATIC7A substation interconnection queue
4 active projects totaling 2,905 MW in the ERCOT queue.
4 ERCOT queue filings name Tap DULCE7A - STATIC7A as the point of interconnection, all in Victoria County, TX.
Target commercial operation dates as filed run from May 2030 to Jun 2033 (4 filings). 4 active filings target a date after November 27, 2026.
Interconnecting entity as filed: Sister 1, LLC (2 filings), Brother 1, LLC (2 filings).
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| 33INR0007 | Blue Energy Center - Phase 3 – Steam Stage 2 | 345 | 1,320 | Nuclear | SS Started, FIS Started, No IA | Jun 2033 |
| 30INR0150 | Blue Energy Center- Phase 1a - Gas | 345 | 780 | Gas | SS Started, FIS Started, No IA | May 2030 |
| 32INR0009 | Blue Energy Center - Phase 2b – Steam | 345 | 475 | Gas | SS Started, FIS Started, No IA | Dec 2032 |
| 29INR0248 | Blue Energy Center - Phase 1b – Steam | 345 | 330 | Gas | SS Completed, FIS Started, No IA | Oct 2031 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.
Tracked changes at this substation
5 changes to filings at this point of interconnection, observed between weekly snapshots of the ERCOT queue. For a capacity revision MW is the change, not the new total.
| Detected | Queue ID | Change | MW | Status was → now |
|---|---|---|---|---|
| 2026-11-09 | 32INR0009 | New request | 475 | Not reported → SS Started, FIS Started, No IA |
| 2026-10-05 | 33INR0007 | New request | 1,320 | Not reported → SS Started, FIS Started, No IA |
| 2026-10-05 | 30INR0150 | New request | 780 | Not reported → SS Started, FIS Started, No IA |
| 2026-10-05 | 29INR0248 | Capacity revised | −780 | SS Completed, FIS Started, No IA → SS Completed, FIS Started, No IA |
| 2026-09-07 | 29INR0248 | Capacity revised | −154.6 | SS Completed, FIS Started, No IA → SS Completed, FIS Started, No IA |
Other ERCOT queue substations in Victoria County, TX
- Tap (Bus #) FURHMANSB8 - (Bus #) VANDERBLTSW8: 2 active, 390.7 MW of 2 filed
- To the line from EDNA (#) to VICTORIA4A (#): 2 active, 332 MW of 2 filed