Tri-X Solar 1 SLF
ERCOT queue ID 20INR0143
Tri-X Solar 1 SLF (20INR0143) is listed in the ERCOT interconnection queue as a 201.5 MW solar project in Crane County, TX. The filing names Soda Lake (#) as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, IA”, with a target commercial operation date of October 30, 2028. It records the screening study as complete on November 8, 2016 and the interconnection agreement as signed on August 21, 2026.
| Queue ID | 20INR0143 |
|---|---|
| Project name | Tri-X Solar 1 SLF |
| Status (as published) | SS Completed, FIS Started, IA |
| Substation | Soda Lake (#) |
| Point of interconnection | 138 kV Soda Lake (#76026) |
| County | Crane |
| State | TX |
| Voltage | 138 kV |
| Capacity | 201.5 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2028-10-30 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Soda Lake (#) substation: 4 requests in the ERCOT queue, 4 active totaling 813.9 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| 24INR0383 | Soda Lake BESS 2 SLF | 205.4 | Battery | SS Completed, FIS Started, IA |
| 28INR0389 | Tri-X BESS 1 SLF | 205.3 | Battery | SS Completed, FIS Started, IA |
| 23INR0080 | Soda Lake Solar 2 SLF | 201.7 | Solar | SS Completed, FIS Started, IA |
Crane, TX: 14 requests in the ERCOT queue, 13 active totaling 2,944.5 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | Crane I Solar Electric, LLC |
|---|---|
| CDR reporting zone | WEST |
| Fuel code | SOL |
| Technology code | PV |
| Interconnection agreement signed | 2026-08-21 |
| Screening study complete | 2016-11-08 |
| Air permit | Not Required |
| Water availability | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.