RIONOG substation interconnection queue

2 active projects totalling 6.2 MW in the ERCOT queue.

2active projects
6.2active MW
2total filed
Queue IDProjectkVMWResourceStatus
24INR0602 CPS Rio Nogales CT301 Rotor Replacement 345 3.1 Gas In Queue
25INR0665 CPS Rio Nogales CT201 Rotor Replacement 345 3.1 Gas In Queue

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.