CPS Rio Nogales CT301 Rotor Replacement (24INR0602) is listed in the ERCOT interconnection queue as a 3.1 MW gas project in Guadalupe County, TX. The filing names RIONOG as its point of interconnection. ERCOT lists its status as “In Queue”, with a target commercial operation date of August 7, 2026. It records the interconnection agreement as signed on November 10, 2023.

Queue ID24INR0602
Project nameCPS Rio Nogales CT301 Rotor Replacement
Status (as published)In Queue
SubstationRIONOG
Point of interconnection5362 RIONOG 345kV
CountyGuadalupe
StateTX
Voltage345 kV
Capacity3.1 MW
Resource (as published)GAS/CC
Resource categoryGas (normalized for filtering)
Target commercial operation2026-08-07
Source datasetsmall

Same substation and county

RIONOG substation: 2 requests in the ERCOT queue, 2 active totaling 6.2 MW.

Queue IDProjectMWResourceStatus
25INR0665CPS Rio Nogales CT201 Rotor Replacement3.1GasIn Queue

Guadalupe, TX: 20 requests in the ERCOT queue, 16 active totaling 3,904 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityCPS Energy
CDR reporting zoneSOUTH
Fuel codeGAS
Technology codeCC
Interconnection agreement signed2023-11-10

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first