Castillo substation interconnection queue
2 active projects totaling 190 MW in the ERCOT queue.
2 ERCOT queue filings name Castillo as the point of interconnection, all in Upton County, TX.
Target commercial operation dates as filed run from Dec 2025 to Dec 2027 (2 filings). 1 active filing targets a date after November 27, 2026.
Interconnecting entity as filed: CED Development Inc. (1 filing), ConEd Development (1 filing).
2active projects
190active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| 24INR0393 | ELECTRODE BESS | 138 | 150 | Battery | SS Completed, FIS Started, No IA | Dec 2027 |
| 19INR0189 | SP TX-12B Phase III | 138 | 40 | Solar | SS Completed, FIS Started, No IA | Dec 2025 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.
Other ERCOT queue substations in Upton County, TX
- Twelvemile: 2 active, 798 MW of 2 filed
- Tap Bearkat - L_NORTMC5_1Y: 2 active, 419.1 MW of 2 filed