Substation Scout

Twelvemile substation interconnection queue

2 active projects totalling 798 MW in the ERCOT queue.

2active projects
798active MW
2total filed
Queue IDProjectkVMWResourceStatus
24INR0404 Tres Rios Ranch Solar 345 508 Solar SS Completed, FIS Started, IA
25INR0451 Tres Rios Ranch BESS 345 290 Battery SS Completed, FIS Started, IA

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.