Bitter Creek
Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Nolan County. First named in the release with data as of June 1, 2025.
Nolancounty as printed
345kV
LCRATSC, ONCORutility
2projects listed
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Nolan, TX: ERCOT queue, 18 active of 18. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Bitter_Creek_Substation_Upgrade Oncor will upgrade the existing 345-kV double-circuit transmission lines Bitter Creek - Morgan Creek (Cattleman) and Bitter Creek - Sweetwater East. Part of the Permian Basin Reliability Plan released by ERCOT, under transmission upgrades L24 ERCOT project 91399 · utility no. PLC-8256 |
LCRATSC Tier 4 |
Planned Future tab |
345 | Jun 2028 | Bitter Creek to Bitter Creek Nolan County |
Bitter Creek |
| Oak Spring (fka Roscoe, Plowboy) 345/138 kV Switch Add Permian Basin Reliability Plan Upgrade ID L25A and L25B. Establish a new Roscoe 345/138-kV substation near the Sweetwater Tap (1341) and install two new 345/138-kV transformers. Loop the existing Sweetwater East - Champion Creek/Bitter Creek - Cattleman 345-kV double-circuit line into Roscoe. ERCOT project 99353 · utility no. R8613 |
ONCOR Tier 3 |
Planned Future tab |
345 | May 2027 | No terminals printed Nolan County |
Roscoe, Bitter Creek, Cattleman |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| July 13, 2026 | 91399 | Projected in-service date | May 2030 → Jun 2028 |
| October 1, 2025 | 99353 | First listed | on the Future tab |
| June 1, 2025 | 91399 | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.