Sim Gideon Combined Cycle

ERCOT queue ID 30INR0051

Queue ID30INR0051
Project nameSim Gideon Combined Cycle
Status (as published)SS Completed, FIS Started, IA
Substation(#) SIM GIDEON
Point of interconnection(#7310) SIM GIDEON 138 kV
CountyBastrop
StateTX
Voltage138 kV
Capacity880 MW
Resource (as published)GAS/CC
Resource categoryGas (normalised for filtering)
Target commercial operation2030-12-15
Source datasetlarge

Additional filed fields

Interconnecting EntityLCRA
Cdr ZoneSOUTH
Fuel CodeGAS
Technology CodeCC
Ia Signed46010
Screening Study Complete45917