Substation Scout

Paintbrush BESS1

ERCOT queue ID 29INR0222

Paintbrush BESS1 (29INR0222) is listed in the ERCOT interconnection queue as a 201.3 MW battery project in Coleman County, TX. The filing names Tap Brown Switch – Bluff Creek Switch & Brown Switch – Central Bluff Switch as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of October 15, 2030. It records the screening study as complete on April 7, 2026.

Queue ID29INR0222
Project namePaintbrush BESS1
Status (as published)SS Completed, FIS Started, No IA
SubstationTap Brown Switch – Bluff Creek Switch & Brown Switch – Central Bluff Switch
Point of interconnectionTap 345kV 1444 Brown Switch – 60040 Bluff Creek Switch & 1444 Brown Switch – 11406 Central Bluff Switch
CountyColeman
StateTX
Voltage345 kV
Capacity201.3 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalized for filtering)
Target commercial operation2030-10-15
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Tap Brown Switch – Bluff Creek Switch & Brown Switch – Central Bluff Switch substation: 5 requests in the ERCOT queue, 5 active totaling 1,207.3 MW.

Queue IDProjectMWResourceStatus
28INR0469Paintbrush PV1251.5SolarSS Completed, FIS Started, No IA
28INR0470Paintbrush PV2251.5SolarSS Completed, FIS Started, No IA
29INR0220Paintbrush PV3251.5SolarSS Completed, FIS Started, No IA
29INR0221Paintbrush PV4251.5SolarSS Completed, FIS Started, No IA

Coleman, TX: 9 requests in the ERCOT queue, 7 active totaling 1,746.6 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityRenew Development HoldCo LLC
CDR reporting zoneWEST
Fuel codeOTH
Technology codeBA
Screening study complete2026-04-07

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first