Tap Brown Switch – Bluff Creek Switch & Brown Switch – Central Bluff Switch substation interconnection queue

5 active projects totalling 1,207.3 MW in the ERCOT queue.

5active projects
1,207.3active MW
5total filed
Queue IDProjectkVMWResourceStatus
28INR0469 Paintbrush PV1 345 251.5 Solar SS Completed, FIS Started, No IA
28INR0470 Paintbrush PV2 345 251.5 Solar SS Completed, FIS Started, No IA
29INR0220 Paintbrush PV3 345 251.5 Solar SS Completed, FIS Started, No IA
29INR0221 Paintbrush PV4 345 251.5 Solar SS Completed, FIS Started, No IA
29INR0222 Paintbrush BESS1 345 201.3 Battery SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.