Paintbrush PV2

ERCOT queue ID 28INR0470

Queue ID28INR0470
Project namePaintbrush PV2
Status (as published)SS Completed, FIS Started, No IA
SubstationTap Brown Switch – Bluff Creek Switch & Brown Switch – Central Bluff Switch
Point of interconnectionTap 345kV 1444 Brown Switch – 60040 Bluff Creek Switch & 1444 Brown Switch – 11406 Central Bluff Switch
CountyColeman
StateTX
Voltage345 kV
Capacity251.5 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2030-05-15
Source datasetlarge

Additional filed fields

Interconnecting EntityRenew Development HoldCo LLC
Cdr ZoneWEST
Fuel CodeSOL
Technology CodePV
Screening Study Complete46041
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.