Foard, TX interconnection queue

4 active projects totalling 1,087.7 MW in the ERCOT queue.

4active projects
1,087.7active MW
4total filed
Queue IDProjectkVMWResourceStatus
23INR0140 Seine BESS 345 308.9 Battery SS Completed, FIS Started, IA
29INR0326 Montgomery Ranch 2 Wind n/r 301.5 Wind SS Started, FIS Started, No IA
28INR0476 Pease River Solar 345 276.4 Solar SS Completed, FIS Started, No IA
28INR0535 Daisy Solar 345 200.9 Solar SS Started, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.