Second Division Storage
ERCOT queue ID 25INR0378
Second Division Storage (25INR0378) is listed in the ERCOT interconnection queue as a battery request filed at 0 MW (a net change or energy-only filing) in Brazoria County, TX. The filing names Tap SANBER_POI_8 (Bus# ) to WEST COLUMBIA (Bus# ) Ckt 60 Line as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of December 31, 2025. It records the screening study as complete on July 13, 2023.
| Queue ID | 25INR0378 |
|---|---|
| Project name | Second Division Storage |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | Tap SANBER_POI_8 (Bus# ) to WEST COLUMBIA (Bus# ) Ckt 60 Line |
| Point of interconnection | Tap 138 kV SANBER_POI_8 (Bus# 43110) to WEST COLUMBIA (Bus# 43380) Ckt 60 Line |
| County | Brazoria |
| State | TX |
| Voltage | 138 kV |
| Capacity | 0 MW (0 MW as filed — net change or energy-only) |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2025-12-31 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Tap SANBER_POI_8 (Bus# ) to WEST COLUMBIA (Bus# ) Ckt 60 Line substation: 2 requests in the ERCOT queue, 2 active totaling 100.2 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| 20INR0248 | DAMAZO (Second Division) SOLAR | 100.2 | Solar | SS Completed, FIS Completed, IA |
Brazoria, TX: 63 requests in the ERCOT queue, 54 active totaling 10,984.8 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | Mound Creek Storage, LLC |
|---|---|
| CDR reporting zone | COASTAL |
| Fuel code | OTH |
| Technology code | BA |
| Screening study complete | 2023-07-13 |