Goliad, TX interconnection queue
14 active projects totalling 2,666.5 MW in the ERCOT queue, plus 1 with terminal status (shown greyed).
14active projects
2,666.5active MW
15total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 26INR0664 | Coleto Creek - Fuel Change Only | 138 | 655 | Gas | SS Completed, FIS Started, No IA |
| 27INR0149 | Diablo Campo Storage | n/r | 313.5 | Battery | SS Completed, FIS Started, No IA |
| 21INR0223 | Tulsita Solar | 138 | 256.2 | Solar | SS Completed, FIS Completed, IA |
| 28INR0303 | Kuy Creek Solar 1 SLF | 138 | 234.9 | Solar | SS Completed, FIS Started, No IA |
| 27INR0144 | Angel City Solar | n/r | 221 | Solar | SS Completed, FIS Started, No IA |
| 24INR0065 | Keys Hollow Solar Phase II SLF | 345 | 200.9 | Solar | SS Completed, FIS Started, IA |
| 24INR0067 | KEYS HOLLOW SOLAR SLF | 345 | 200.9 | Solar | SS Completed, FIS Started, IA |
| 28INR0304 | Kuy Creek Storage 1 SLF | 138 | 151.5 | Battery | SS Completed, FIS Started, No IA |
| 23INR0206 | PEREGRINE BESS | 345 | 150 | Battery | SS Completed, FIS Started, No IA |
| 25INR0078 | Peregrine BESS 2 | 345 | 150 | Battery | SS Completed, FIS Started, No IA |
| 27INR0248 | Double A Solar SLF | 69 | 132.6 | Solar | SS Completed, FIS Started, No IA |
| 22INR0275 | Coleto Creek ESS Addition | n/r | 100.1 | Battery | Inactive |
| 24INR0066 | Keys Hollow Storage Phase II SLF | 345 | 0 | Battery | SS Completed, FIS Started, IA |
| 24INR0068 | KEYS HOLLOW STORAGE SLF | 345 | 0 | Battery | SS Completed, FIS Started, IA |
| 27INR0257 | Double A Storage SLF | 69 | 0 | Battery | SS Completed, FIS Started, No IA |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.