Kuy Creek Solar 1 SLF

ERCOT queue ID 28INR0303

Queue ID28INR0303
Project nameKuy Creek Solar 1 SLF
Status (as published)SS Completed, FIS Started, No IA
SubstationTap Coleto Creek (Bus # ) - Victoria (Bus# ) CKT 1
Point of interconnectionTap Coleto Creek (Bus # 8162) - Victoria (Bus# 8172) 138 kV CKT 1
CountyGoliad
StateTX
Voltage138 kV
Capacity234.9 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2029-03-20
Source datasetlarge

Additional filed fields

Interconnecting EntityKuy Creek Solar 1 LLC
Cdr ZoneSOUTH
Fuel CodeSOL
Technology CodePV
Screening Study Complete45826
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.