Callahan, TX interconnection queue

5 active projects totalling 1,570.6 MW in the ERCOT queue.

5active projects
1,570.6active MW
5total filed
Queue IDProjectkVMWResourceStatus
22INR0262 Sequoia II Solar 345 417.5 Solar SS Completed, FIS Completed, IA
28INR0245 Hittson Creek Solar 345 402.9 Solar SS Completed, FIS Started, No IA
20INR0083 Baird North Wind 345 340 Wind SS Completed, FIS Completed, IA
28INR0246 Hittson Creek BESS 345 205.4 Battery SS Completed, FIS Started, No IA
25INR0446 Guitar BESS 138 204.8 Battery SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.