Substation Scout

Hittson Creek Solar

ERCOT queue ID 28INR0245

Queue ID28INR0245
Project nameHittson Creek Solar
Status (as published)SS Completed, FIS Started, No IA
SubstationTapping the two Lines: Sam Line Reactor (Bus# ) - Reata (Bus# ) and Latimer (Bus# ) - Reata (Bus# ).
Point of interconnectionTapping the two 345 kV Lines: Sam Line Reactor (Bus# 68005) - Reata (Bus# 68051) and Latimer (Bus# 68008) - Reata (Bus# 68051).
CountyCallahan
StateTX
Voltage345 kV
Capacity402.9 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2028-12-15
Source datasetlarge

Additional filed fields

Interconnecting Entity174 Power Global Properties
Cdr ZoneWEST
Fuel CodeSOL
Technology CodePV
Screening Study Complete45734
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.