Substation Scout

Baird North Wind

ERCOT queue ID 20INR0083

Queue ID20INR0083
Project nameBaird North Wind
Status (as published)SS Completed, FIS Completed, IA
SubstationLatimer
Point of interconnection68008 Latimer 345kV
CountyCallahan
StateTX
Voltage345 kV
Capacity340 MW
Resource (as published)WIN/WT
Resource categoryWind (normalised for filtering)
Target commercial operation2026-12-31
Source datasetlarge

Additional filed fields

Interconnecting EntityBMP Wind, LLC
Cdr ZoneWEST
Fuel CodeWIN
Technology CodeWT
Ia Signed43616
Screening Study Complete43263
Fis Approved44134
Air PermitNot Required
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.