Substation Scout

Lookout Point-Alvey No. 1 line substation interconnection queue

0 active projects totalling 0 MW in the BPA queue, plus 2 with terminal status (shown greyed).

0active projects
0active MW
2total filed
Queue IDProjectkVMWResourceStatus
G0881 Not reported 115 80 Solar WITHDRAWN
G0882 Not reported 115 80 Solar WITHDRAWN

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with BPA before relying on these figures.