Lane, OR interconnection queue
5 active projects totalling 33.5 MW in the BPA queue, plus 24 with terminal status (shown greyed).
5active projects
33.5active MW
29total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| G0811 | Not reported | 230 | 600 | Other | WITHDRAWN |
| G0812 | Not reported | 230 | 600 | Battery | WITHDRAWN |
| G46 | Coburg Power | 500 | 570 | Gas | WITHDRAWN |
| G0918 | Not reported | 230 | 300 | Wind | WITHDRAWN |
| G36 | Frontier Technology | 500 | 265 | Gas | WITHDRAWN |
| G0803 | Not reported | n/r | 200 | Battery | WITHDRAWN |
| G0810 | Not reported | 230 | 200 | Other | WITHDRAWN |
| G0888 | Not reported | 230 | 200 | Solar | WITHDRAWN |
| G0889 | Not reported | 230 | 200 | Battery | WITHDRAWN |
| G0890 | Not reported | 230 | 200 | Solar | WITHDRAWN |
| G0891 | Not reported | 230 | 200 | Solar | WITHDRAWN |
| G1046 | Not reported | 115 | 100 | Battery | WITHDRAWN |
| G0802 | Not reported | 115 | 80 | Other | WITHDRAWN |
| G0877 | Not reported | 115 | 80 | Other | WITHDRAWN |
| G0879 | Not reported | 115 | 80 | Solar | WITHDRAWN |
| G0880 | Not reported | 115 | 80 | Solar | WITHDRAWN |
| G0881 | Not reported | 115 | 80 | Solar | WITHDRAWN |
| G0882 | Not reported | 115 | 80 | Solar | WITHDRAWN |
| G0883 | Not reported | n/r | 80 | Other | WITHDRAWN |
| G0884 | Not reported | n/r | 80 | Battery | WITHDRAWN |
| G0971 | Not reported | 115 | 80 | Other | WITHDRAWN |
| G1044 | Not reported | 115 | 21 | Battery | WITHDRAWN |
| G0349 | Senaca Sawmill | n/r | 20 | Other | ENERGIZED |
| G0453 | University of Oregon CoGeneration | n/r | 11 | Gas | ENERGIZED |
| G0439 | Not reported | n/r | 2 | Other | Decommissioned (terminated) |
| G1075 | Not reported | 115 | 1.1 | Solar | STUDY |
| G0332 | King Estate Solar Generator Project | n/r | 1 | Solar | ENERGIZED |
| G0594 | Not reported | n/r | 1 | Solar | WITHDRAWN |
| G1077 | Not reported | 115 | 0.4 | Solar | STUDY |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with BPA before relying on these figures.