Lane, OR interconnection queue

5 active projects totalling 33.5 MW in the BPA queue, plus 24 with terminal status (shown greyed).

5active projects
33.5active MW
29total filed
Queue IDProjectkVMWResourceStatus
G0811 Not reported 230 600 Other WITHDRAWN
G0812 Not reported 230 600 Battery WITHDRAWN
G46 Coburg Power 500 570 Gas WITHDRAWN
G0918 Not reported 230 300 Wind WITHDRAWN
G36 Frontier Technology 500 265 Gas WITHDRAWN
G0803 Not reported n/r 200 Battery WITHDRAWN
G0810 Not reported 230 200 Other WITHDRAWN
G0888 Not reported 230 200 Solar WITHDRAWN
G0889 Not reported 230 200 Battery WITHDRAWN
G0890 Not reported 230 200 Solar WITHDRAWN
G0891 Not reported 230 200 Solar WITHDRAWN
G1046 Not reported 115 100 Battery WITHDRAWN
G0802 Not reported 115 80 Other WITHDRAWN
G0877 Not reported 115 80 Other WITHDRAWN
G0879 Not reported 115 80 Solar WITHDRAWN
G0880 Not reported 115 80 Solar WITHDRAWN
G0881 Not reported 115 80 Solar WITHDRAWN
G0882 Not reported 115 80 Solar WITHDRAWN
G0883 Not reported n/r 80 Other WITHDRAWN
G0884 Not reported n/r 80 Battery WITHDRAWN
G0971 Not reported 115 80 Other WITHDRAWN
G1044 Not reported 115 21 Battery WITHDRAWN
G0349 Senaca Sawmill n/r 20 Other ENERGIZED
G0453 University of Oregon CoGeneration n/r 11 Gas ENERGIZED
G0439 Not reported n/r 2 Other Decommissioned (terminated)
G1075 Not reported 115 1.1 Solar STUDY
G0332 King Estate Solar Generator Project n/r 1 Solar ENERGIZED
G0594 Not reported n/r 1 Solar WITHDRAWN
G1077 Not reported 115 0.4 Solar STUDY

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with BPA before relying on these figures.