Substation Scout

Tucannon River Wind Farm

BPA queue ID G0286

Queue IDG0286
Project nameTucannon River Wind Farm
Status (as published)ENERGIZED
SubstationCentral Ferry Substation
Point of interconnectionCentral Ferry Substation
CountyColumbia & Garfield
StateWA
VoltageNot reported
Capacity250 MW
Resource (as published)Wind Turbine/Wind Turbine
Resource categoryWind (normalised for filtering)
Target commercial operation2011-12-31
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

RequestorPortland General Electric Company
Connection TypeGI
Interconnection TypeNRIS
PoiCentral Ferry Substation
Generator TypeWind Turbine
Fuel SourceWind Turbine
Nameplate Mw Total250
Max Summer Mw250
Max Winter Mw250
Reason Not Completed.
CommentsPhase 2 for 267 MW acquired by PGE; on-line scheduled for December 2014.

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.