Tucannon River Wind Farm
BPA queue ID G0286
| Queue ID | G0286 |
|---|---|
| Project name | Tucannon River Wind Farm |
| Status (as published) | ENERGIZED |
| Substation | Central Ferry Substation |
| Point of interconnection | Central Ferry Substation |
| County | Columbia & Garfield |
| State | WA |
| Voltage | Not reported |
| Capacity | 250 MW |
| Resource (as published) | Wind Turbine/Wind Turbine |
| Resource category | Wind (normalised for filtering) |
| Target commercial operation | 2011-12-31 |
| Source dataset | bpa-generation |
Tracked changes
No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →
Additional filed fields
| Requestor | Portland General Electric Company |
|---|---|
| Connection Type | GI |
| Interconnection Type | NRIS |
| Poi | Central Ferry Substation |
| Generator Type | Wind Turbine |
| Fuel Source | Wind Turbine |
| Nameplate Mw Total | 250 |
| Max Summer Mw | 250 |
| Max Winter Mw | 250 |
| Reason Not Completed | . |
| Comments | Phase 2 for 267 MW acquired by PGE; on-line scheduled for December 2014. |