Lower Snake Phase 1
BPA queue ID G0285
| Queue ID | G0285 |
|---|---|
| Project name | Lower Snake Phase 1 |
| Status (as published) | ENERGIZED |
| Substation | Central Ferry Substation |
| Point of interconnection | Central Ferry Substation |
| County | Garfield & Columbia |
| State | WA |
| Voltage | Not reported |
| Capacity | 250 MW |
| Resource (as published) | Wind Turbine/Wind Turbine |
| Resource category | Wind (normalised for filtering) |
| Target commercial operation | 2011-12-31 |
| Source dataset | bpa-generation |
Tracked changes
No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →
Additional filed fields
| Requestor | Puget Sound Energy, Inc. |
|---|---|
| Connection Type | GI |
| Interconnection Type | NRIS |
| Poi | Central Ferry Substation |
| Generator Type | Wind Turbine |
| Fuel Source | Wind Turbine |
| Nameplate Mw Total | 150 |
| Max Summer Mw | 250 |
| Max Winter Mw | 250 |
| Reason Not Completed | . |
| Comments | Phase I for 93 MW; on-line January 2012 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.