Tollway

Named in 4 PJM planning documents for 3 projects, from September 9, 2025 to July 7, 2026.

Existingdescribed as
COMEDzone
138 kV, 345kVkV as printed
4mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Customer in Hoffman Estates
ComEd-2024-005 · s3578.1
Engineering $3M 12/31/26 324 MW 2025-10-08
TEAC
Customer in Hoffman Estates
ComEd-2024-016
Conceptual $84.8M 9/1/2028 612 MW 2025-09-09
TEAC
Customer in Grayslake
ComEd-2025-005
Conceptual $248.8M 6/1/2027 (Phase 1), 6/1/2029 (Phase 2), 6/1/2030 (Phase 3), 6/1/2029 (138KV System Reinforcement), 6/1/2030 (345KV Auto, 345KV Silverlake-Grayslake, 345KV Wayne-Tollway), 6/1/2031 (345KV Tollway-Grayslake) 1,550 MW 2026-07-07
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate $174.8M → $248.8M 2026-03-10 2026-07-07
In-service date 6/30/2027 (Phase 1), 6/30/2029 (Phase 2), 6/30/2030 (Phase 3), 6/1/2029 (System Reinforcement) → 6/1/2027 (Phase 1), 6/1/2029 (Phase 2), 6/1/2030 (Phase 3), 6/1/2029 (138KV System Reinforcement), 6/1/2030 (345KV Auto, 345KV Silverlake-Grayslake, 345KV Wayne-Tollway), 6/1/2031 (345KV Tollway-Grayslake) 2026-03-10 2026-07-07
Substations named BEVERLY ROAD; GRAYSLAKE; HANOVER TAP; LIBERTYVILLE; SILVER LAKE; SPAULDING → GRAYSLAKE; HANOVER TAP BLUE; HANOVER TAP RED; LIBERTYVILLE; SILVER LAKE; SPAULDING; TOLLWAY; WAYNE 2026-03-10 2026-07-07

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
ComEd local plan submission of the supplemental projects for 2025 RTEP p. 3
Customer in Hoffman Estates “from Tollway substation to the customer site”
138 kV
2026-07-07 TEAC
Item 12 - ComEd Supplemental Projects p. 9
Customer in Grayslake “Cut into existing 345kV Tollway - Libertyville line”
345kV
2025-10-08 TEAC
Informational Only - ComEd Local Plan Submission of the Supplemental Projects for 2025 p. 3
Customer in Hoffman Estates “At Tollway, replace 138 kV BT 2-3 CB with two 138kV BT CBs”
138 kV
2025-09-09 TEAC
Item 12 - ComEd Supplemental Projects p. 18
Customer in Hoffman Estates “Cut into existing 345kV Libertyville – Tollway line”
345kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.