Rahway

Named in 4 PJM planning documents for 3 projects, from October 8, 2024 to November 13, 2025.

Existingdescribed as
PSEGzone
69 kV, 69kVkV as printed
4mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Rahway - Roselle 69kV Line
b4019.1
Not printed $29.4 M 12/31/2029 Not printed 2025-11-13
SRRTEP Mid-Atlantic
Rahway - Roselle 69kV Line Not printed $29.4 M 12/31/2029 Not printed 2025-10-16
SRRTEP Mid-Atlantic
Perth Amboy Area
PSEG-2023-0007 · s3009
Engineering $220.68M 12/2028 Not printed 2024-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Mid-Atlantic
PSEG local plan submission for 2024 RTEP p. 9
Perth Amboy Area “Build a new 69kV line to Rahway station”
69kV
2025-11-13 SRRTEP Mid-Atlantic
Item 01 - SRRTEP Mid-Atlantic - Reliability Analysis Update p. 7
Rahway - Roselle 69kV Line No role wording
2025-10-16 SRRTEP Mid-Atlantic
Item 02 - SRRTEP Mid-Atlantic - Reliability Analysis Update p. 7
Rahway - Roselle 69kV Line “Reconductor 69kV line from Rahway to Roselle Station”
69 kV
2024-10-08 TEAC
Informational Only - PSEG Local Plan submission of supplemental project 2024 p. 9
Perth Amboy Area “Build a new 69kV line to Rahway station.”
69kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this