Blair Road

Named in 2 PJM planning documents for 2 projects, from October 16, 2025 to November 13, 2025.

Not stateddescribed as
PSEGzone
69kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Rahway - Roselle 69kV Line
b4019.1
Not printed $29.4 M 12/31/2029 Not printed 2025-11-13
SRRTEP Mid-Atlantic
Rahway - Roselle 69kV Line Not printed $29.4 M 12/31/2029 Not printed 2025-10-16
SRRTEP Mid-Atlantic

Every mention

DateDocumentProjectWhat the document says about it
2025-11-13 SRRTEP Mid-Atlantic
Item 01 - SRRTEP Mid-Atlantic - Reliability Analysis Update p. 8
Rahway - Roselle 69kV Line No role wording
2025-10-16 SRRTEP Mid-Atlantic
Item 02 - SRRTEP Mid-Atlantic - Reliability Analysis Update p. 8
Rahway - Roselle 69kV Line No role wording
69kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.