Burlington
Named in 3 PJM planning documents for 1 project, from September 9, 2025 to October 6, 2026.
PJM interconnection queue
A PJM queue substation page has the same name: Burlington (NJ) — 24 queue requests filed, 9 active.
Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| Mount Laurel Area PSEG-2024-0004 · s3754.1 |
Engineering | $85.0M | May 2031 | Not printed | 2026-10-06 TEAC |
Changes between documents
Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.
| What changed | Printed values | Earlier | Later |
|---|---|---|---|
| In-service date | 05/2031 → May 2031 | 2025-09-09 | 2026-10-06 |
| Status | conceptual (Conceptual) → engineering (Engineering and Planning) | 2025-09-09 | 2026-10-06 |
| Substations named | BRIGGS RD; BURLINGTON; COXS CORNER; CREEK RD; LUMBERTON; MOUNT HOLLY; MOUNT LAUREL → BURLINGTON; COXS CORNER; CREEK RD; MOUNT LAUREL | 2025-09-09 | 2026-10-06 |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-10-06 | TEAC Informational Only - PSEG Local Plan Submission of the Supplemental Projects for 2026.xlsx p. 5 |
Mount Laurel Area | No role wording 230kV |
| 2026-09-08* | SRRTEP Mid-Atlantic PSEG local plan submission for 2026 RTEP p. 5 |
Mount Laurel Area | No role wording 230kV |
| 2025-09-09 | TEAC Item 15 - PSEG Supplemental Projects p. 4 |
Mount Laurel Area | “Cut and loop Cox’s Corner - Burlington 230kV circuit into new substation.” 230kV |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.