Substation Scout

Briggs Rd

Named in 1 PJM planning document for 1 project, on September 9, 2025.

Newdescribed as
PSEGzone
69kVkV as printed
1mentions

Described as new: “Purchase property and construct a 69kV substation at Briggs Rd.” — source, page 4

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Mount Laurel Area
PSEG-2024-0004
Conceptual $85.0M 05/2031 Not printed 2025-09-09
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
In-service date 05/2031 → May 2031 2025-09-09 2026-10-06
Status conceptual (Conceptual) → engineering (Engineering and Planning) 2025-09-09 2026-10-06
Substations named BRIGGS RD; BURLINGTON; COXS CORNER; CREEK RD; LUMBERTON; MOUNT HOLLY; MOUNT LAUREL → BURLINGTON; COXS CORNER; CREEK RD; MOUNT LAUREL 2025-09-09 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2025-09-09 TEAC
Item 15 - PSEG Supplemental Projects p. 4
Mount Laurel Area “Purchase property and construct a 69kV substation at Briggs Rd.”
69kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this