Muncy-Tie

Named in 1 PJM planning document for 1 project, on October 6, 2026.

Not stateddescribed as
PPLzone
—kV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Fairfield, PA
PPL-2026-0008
Conceptual $0.2 M 10/08/2028 Not printed 2026-10-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named FAIRFIELD; LYCOMING; MUNCY TIE → FAIRFIELD; LYCOMING; MUNCY 2026-10-06 Not reported
Substations named FAIRFIELD → CLINTON; FAIRFIELD; LYCOMING 2026-01-15 2026-02-12
Substations named CLINTON; FAIRFIELD; LYCOMING → FAIRFIELD; LYCOMING; MUNCY TIE 2026-02-12 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - PPL Local Plan Submission of the Supplemental Projects for 2026 p. 49
Fairfield, PA No role wording

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.