Clark Street

Named in 1 PJM planning document for 1 project, on March 18, 2026.

Not stateddescribed as
JCPLzone
34.5 kVkV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
EH Werner- Freneau- Keyport 34.5 kV E31 Line, PA
JCPL-2024-012
Conceptual $22.50M 05/11/2029 Not printed 2026-03-18
SRRTEP Mid-Atlantic

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named EH WERNER; FRENEAU; KEYPORT → FRENEAU; KEYPORT 2026-10-06 Not reported
Substations named CLARK STREET; EH WERNER; FELTUS ST; FRENEAU; KEYPORT; LAURENCE HARBOR → EH WERNER; FRENEAU; KEYPORT 2026-03-18 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2026-03-18 SRRTEP Mid-Atlantic
Item 06 - JCPL Supplemental Projects p. 10
EH Werner- Freneau- Keyport 34.5 kV E31 Line, PA No role wording
34.5 kV