Mountain View
Named in 3 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).
—county (not printed)
—kV in the quote
GPCproject sponsor
3projects in the plan
The plan prints no county for this substation, and no utility project page found names one for it.
Projects naming this substation
As the plan prints them. The sponsor is the project’s; one project can split work between owners.
| Project | Sponsor | Where in the plan | Need date | Change from the previous plan | Substations named |
|---|---|---|---|---|---|
| MORROW - MOUNTAIN VIEW 115 kV REBUILD Rebuild the 1.7 miles Mountain View - Barnett Road section of the Morrow - Mountain View 115kV line with 200C 1351 ACSS Martin conductor. TEAMS 19363 · plan p.116 · zone 208 |
GPC | In the plan p.9 |
Dec 31, 2026 | No change | Morrow, Mountain View |
| EAST POINT - MORROW 115kV REBUILD Rebuild a 3 miles section of the East Point - Morrow 115kV line, 1.4 mile from East Point to College Point Tap and 1.5 mile from Morrow to Forest Park with 200C 1351 ACSS Martin. Also rebuild portions of Morrow - Mountain View and East Point - Mountain View 115kV lines. TEAMS 21303 · plan p.306 · zone 208 |
GPC | In the plan p.22 |
Jun 1, 2035 | New project | East Point, Morrow, Mountain View |
| EAST POINT - MOUNTAIN VIEW 115kV REBUILD Rebuild a portion of the East Point - Mountain View 115kV line, approximately 2.4 miles of 100C 397.5 ACSR between East Point - College Park # 3 Junction using 200C 1351 ACSS Martin. TEAMS 21335 · plan p.291 · zone 208 |
GPC | In the plan p.21 |
Jun 1, 2033 | New project | East Point, Mountain View |
Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.
Before relying on any of this
- The plan prints no county for a substation. A county shown here is printed in the plan beside the station, or on a Georgia Power or Georgia Transmission project page that names the same station and one county.
- Project Sponsor belongs to the project, not to each station; one project can split work between owners.
- Costs are redacted in the public version of the plan and are not shown.